Doc EF-INS-11821 · OMB M-26-05 and software security: what to ask a developer for

20+ years in business

US-owned · SDVOSB

Sheet Insights

Insights

OMB M-26-05 and software security: what to ask a developer for

If your PWS template still says the contractor “shall submit the CISA self-attestation form per M-22-18”, it cites a rescinded memo. On January 23, 2026, OMB issued M-26-05, Adopting a Risk-based Approach to Software and Hardware Security, and rescinded M-22-18 and its companion, M-23-16 (M-26-05).

That did not take software security out of federal contracts. It moved the decision to each agency. Here is what the memo says, and what is still worth asking a developer for, written from the developer’s side of the table.

What M-26-05 actually says

The memo is two pages. The parts that matter for a contract:

  • “Each agency head is ultimately responsible for assuring the security of software and hardware that is permitted to operate on the agency’s network.”
  • Agencies “may choose to use” the resources developed under M-22-18, such as the Secure Software Development Attestation Form.
  • Agencies “may also choose to adopt contractual terms that require a software producer to provide a current software bill of materials (SBOM) upon request.” For cloud, a footnote asks for “an SBOM of the runtime production environment upon request.”
  • For more options it points to NIST SP 800-218, the Secure Software Development Framework (SSDF).

Whether the attestation form is still required

Not government-wide. The form is now optional, and CISA’s page for it sits in its archive, marked as content that “may not reflect current policy or programs” (CISA).

Optional still leaves the door open. Your agency can require the form, or an SBOM, through its own policy or the solicitation. If you are selling, read the solicitation. If you are buying, the contracting officer and counsel decide whether and how a requirement goes into the contract.

Name SSDF tasks and the evidence for each

The SSDF says its intention “is not to create a checklist to follow” (SP 800-218). So “the contractor shall comply with NIST SP 800-218” is a weak requirement: it names a whole framework and proves none of it. An example under task PO.1.3 points to the better route, a core set of security requirements included “in acquisition documents, software contracts, and other agreements with third parties.”

These are the SSDF contract requirements we would expect a buyer to name for custom development (task IDs from version 1.1):

  • PW.7.2, code review and analysis. Evidence: review or scan results per release, with findings triaged in the issue tracker.
  • PW.8.2, testing executable code. Evidence: documented test results per release.
  • PW.4.4, third-party components. Evidence: a dependency scan per release.
  • PS.2.1, release integrity. “Make software integrity verification information available to software acquirers.” Evidence: hashes or signatures on release files.
  • PS.3.2, provenance. Provenance data for each release’s components, for example an SBOM.
  • RV.1.3, vulnerability disclosure. A written disclosure and remediation policy, and people assigned to run it.

SBOMs: on request, and say which SBOM

If you adopt the M-26-05 term, CISA’s 2026 minimum elements give you words to make it specific (CISA 2026 SBOM minimum elements):

  • Frequency: “Each software version or update should have an associated SBOM.”
  • Coverage: all components, “including transitive dependencies. There is no minimum depth.”
  • Format: SPDX and CycloneDX are the two “currently widely used”, and organizations “should accept any widely used, interoperable, and machine-processable SBOM format.”

The same document says the minimum elements “do not create new requirements”. For a cloud platform, M-26-05’s footnote says the term should cover an SBOM of the runtime production environment, so the application code alone does not meet it. Our piece on federal sites in the cloud covers what the cloud provider owns and what your team owns.

Patch windows bind a contractor only through the contract

CISA’s BOD 26-04, issued June 10, 2026, says: “Unless directed by the governing procurement contract, this Directive does not apply to contractors” (BOD 26-04). If the development team also maintains the system, the directive’s remediation timelines reach that team only through the contract.

The shortest window in the directive’s table is three calendar days, and some three-day entries are marked “& forensic triage”: remediate within the three days and also check whether the system was compromised. That is a staffing and release-pipeline question first. The team needs a tested way to ship a fix outside the normal sprint, and someone with deploy rights available. Write it into the PWS as an outcome, then size the team to it, as our PWS scoping article describes.

SP 800-53 Release 5.2.0: new controls outside every baseline

NIST issued SP 800-53 Release 5.2.0 on August 27, 2025, focused on “the security and reliability of software updates and patches” (NIST). It adds controls including SI-02(07), Root Cause Analysis. NIST’s summary of changes marks every new control as not included in any SP 800-53B baseline. If you want a written root cause analysis after a failed update, select SI-02(07) for the system and say so in the PWS.

Code written with AI tools

NIST SP 800-218A answers a question buyers now ask: its tasks “do not distinguish between human-written and AI-generated source code, because it is assumed that all source code should be evaluated for vulnerabilities and other issues before use” (SP 800-218A). So a PWS can apply PW.7.2 to all code, with no separate regime for generated code.

Each ask and the effort it takes

Effort is relative, for a small team that already uses source control and pull requests. It is not a price.

Ask in the PWSSourceEffort for the team
Code review or static analysis per releaseSSDF PW.7.2Low to run. Triaging findings is the real work.
Dependency scan per releaseSSDF PW.4.4Low on a package-managed build. Higher where libraries were copied in by hand.
SBOM per release, on requestM-26-05; SSDF PS.3.2Low once a build step produces it. High if first asked for at the end.
Hashes or signatures on release filesSSDF PS.2.1Low to produce. Guarding the signing key is the real work.
Vulnerability disclosure policy and contactSSDF RV.1.3Low. A short policy and a person who answers.
Remediation timelines for vulnerabilitiesBOD 26-04, if the contract says soThe big one. Short windows change staffing and on-call coverage.
Root cause analysis after a failed updateSP 800-53 SI-02(07)Low per event: a short written review.
Signed attestation formM-26-05 (optional)Low to sign. Making every statement true is the effort.

What not to write

  • M-22-18 or M-23-16 as the authority. Both are rescinded.
  • That OMB requires an SBOM. M-26-05 says agencies “may” adopt that term.
  • “Comply with SP 800-218” and nothing more. Name the tasks and the evidence.
  • An assumption that BOD 26-04 timelines bind the contractor without the contract saying so.
  • An assumption that the new SP 800-53 controls are in your baseline. They are not in any SP 800-53B baseline.

Where it stands on 16 October 2026

Checked against the current OMB, NIST, CISA, FAR Council, and DARS pages on 16 October 2026.

  • OMB: M-26-05 (January 23, 2026) remains listed by OMB and rescinds M-22-18 and M-23-16. Agencies may choose to use the attestation form; M-26-05 does not make it a government-wide requirement.
  • SSDF: version 1.1 (SP 800-218, February 2022) is final. Version 1.2 was released as an initial public draft on December 17, 2025; comments closed January 30, 2026. Executive Order 14306 calls for a final version within 120 days of the preliminary update. NIST’s SSDF news page lists no final version yet.
  • SBOM minimum elements: CISA published the 2026 version on July 29, 2026, replacing the 2021 NTIA minimum elements (CISA).
  • SP 800-53: Release 5.2.0, August 27, 2025.
  • Patch timelines: BOD 26-04 (June 10, 2026) supersedes and revokes BOD 22-01 and BOD 19-02.
  • FAR: the proposed rule rewriting FAR Part 39 (June 23, 2026) is not final and does not mention attestation, SBOMs or SP 800-218. FAR Case 2023-002, Supply Chain Software Security, is not on the Open FAR Cases report dated October 2, 2026.

What we do

We build custom software for federal and commercial customers; 541511 Custom Computer Programming is our primary NAICS code. Our delivery stack includes Git and Azure DevOps, and our compliance work includes RMF, ATO support and continuous monitoring. Our public register lists cybersecurity on our prime contract for a federal budget office (2022 to now). The full list is on our Work register.

Sources

  1. OMB M-26-05: Adopting a Risk-based Approach to Software and Hardware Security (PDF)
  2. CISA: Secure Software Development Attestation Form (archived)
  3. NIST SP 800-218: Secure Software Development Framework version 1.1 (PDF)
  4. NIST SP 800-218 final publication page
  5. NIST SP 800-218 Rev. 1 initial public draft
  6. NIST SSDF project news
  7. Executive Order 14306
  8. CISA: 2026 Minimum Elements for a Software Bill of Materials (PDF)
  9. CISA: 2026 SBOM minimum elements resource page
  10. CISA: BOD 26-04, Prioritizing Security Updates Based on Risk
  11. NIST: SP 800-53 Release 5.2.0 announcement
  12. NIST: SP 800-53 Release 5.2.0 summary of changes (PDF)
  13. NIST SP 800-53 Rev. 5 Release 5.2.0 publication page
  14. NIST SP 800-218A: SSDF Community Profile for generative AI (PDF)
  15. Federal Register: FAR overhaul proposed rule, June 23, 2026
  16. DARS: Open FAR Cases report (PDF)